Practical completion and what it sets off, the difference between a snag and a defect, retention released in two halves, and how long you are actually liable — which is not the defects period.

Updated 17 September 2026

The end of a job is where the money and the goodwill both go. A homeowner who is delighted on the day can be furious four months later, and it is almost always about the same three things: what "finished" meant, whose fault something is, and when the rest of the money is coming.

Practical completion is an event

Not a status you tick. It is the day the work became usable and the client took the building back, and signing it off in BuildFlow does four things at once:

  1. 1.Starts the defects period.
  2. 2.Makes the first half of any retention due.
  3. 3.Hands responsibility for the building — including insuring it — back to the client.
  4. 4.Tells them, so nobody is working from a different date.

Builders read practical completion as "job's done". Homeowners read it as "everything is finished". Most of what they later argue about lives in the gap between those two readings, which is why BuildFlow asks for a date, a defects period and a note rather than flipping a switch.

It cannot be dated forward

The date is the day it happened, which may not be today. A date set ahead would either be a guess or a way of starting the defects period early, and both produce a record saying something untrue about when the client got their building back.

Signing off does not close your snag list. If items are still open BuildFlow says so — and they are now things somebody is looking at from inside their own house.

A snag is not a defect

SnagDefect
WhenBefore completionAfter it
Who finds itYou, or the client walking round with youWhoever is living there
What it isPart of finishing the jobSomething that has gone wrong since
Where in BuildFlowSnagging tabAftercare tab

They are kept apart deliberately. One list holding both would show "still on the punch list" and "the shower has leaked into the kitchen ceiling" the same way, and those are not the same problem.

The defects register

Anyone on the job can report a defect, the client included. That is the point of it: a register only the builder can write to records what the builder noticed, which is not the problem it exists to solve.

The form asks a homeowner for one thing — what is wrong — plus where, and anything else worth knowing. It does not ask them to categorise it or say whose fault it is. Those are your decisions, and asking the person who found it to guess is how a register fills up with wrong answers.

Whose is it?

Only your side can answer that, and it is worth answering even when the answer is "not ours".

AnswerWhat it commits you to
Our workmanshipYours to put right, at your cost.
A material failedStill yours to sort out with the client. Take it up with the supplier separately.
A subcontractor'sYours to the client either way. Whether they carry it is between you and them.
Under a product warrantyThe guarantee covers it. Help them claim — they will not know how.
Damage after we leftNot yours. Say so kindly, and say what it would cost to fix.
Fair wear and tearNot a defect. Worth explaining what normal looks like.
Working as agreedIt is doing what it was specified to do. Explain rather than argue.

Anything that is not yours needs a reason, and BuildFlow will not record it without one. The client reads what you write. A year of these also tells you something you cannot get any other way — whether your problem is your own work, a trade you keep using, or a product you keep specifying.

Subcontractors cannot decide

They can see the register, because they may be the ones fixing something. They cannot set whose fault it is — the subcontractor whose work is in question deciding whether the defect is theirs is not a rule anybody would write down on purpose.

How long you are actually liable

This is the part that costs people, so it is worth being blunt.

A defects period is not a limitation period. Six or twelve months is a contractual arrangement about who comes back and fixes things for free. It says nothing about how long a homeowner can bring a claim.

Under the Consumer Rights Act 2015 a service must be carried out with reasonable care and skill. Where it was not, a homeowner generally has six years to bring a claim in England, Wales and Northern Ireland, and five in Scotland — and those clocks do not start at practical completion in every case.

So BuildFlow does not close the register

A defect reported after the period ends is recorded like any other and marked as outside it. What changes is who pays, not whether it exists. An app that quietly stopped accepting them at month twelve would be helping a builder believe something that is not true — and the record is what answers a claim three years later.

Retention

Money the client holds back as security that you will come back. Set the percentage on the job's Money tab; the usual arrangement is a few percent, released in two halves.

HalfWhenWhy
FirstAt practical completionThe building is usable and handed back.
SecondAt the end of the defects periodYou came back and fixed what came up.

Held against what has been paid, not what was agreed

On a £40,000 job with 5% retention where £30,000 has actually been received, £1,500 is held — not £2,000. Retention is money withheld from payments made; it cannot be held out of money that has not arrived.

BuildFlow shows what is held, what has been released and what is left, and will not let you release anything before practical completion — there is nothing to release it against. The amounts are recorded rather than calculated rigidly, so a part release or a figure you negotiated survives.

Practical completion can be undone if you got the date wrong, but not once retention has been released against it. The money has moved.

Closing the job

Close the job records final completion — the end of the defects period, certified.

BuildFlow will let you do it with defects still open, deliberately. A builder and a client are perfectly entitled to agree the job is closed with two small things outstanding, and a tool that blocked it would simply be worked around. It tells you what is open and lets you decide.

Guarantees

What is covered, who honours it, and until when. Your own workmanship guarantee, the manufacturer's on the boiler, the installer's on the roof, any insurance-backed policy.

It prints in the handover pack, and it is the page most used five years on. A homeowner with a leaking flat roof rings the builder because the builder is the only name they have — this is what turns that call into a claim on the right person.

What the client sees

  • Reports a defect, and watches where it gets to.
  • The retention position — it is their money being held.
  • The guarantees, because a guarantee nobody knows about is worth nothing.

They do not see whose fault anything is until you have decided, and they cannot change a status or close anything. The register is only useful as a record if one side of it is not writable by the side it is about.

FlowAI knows where a job stands

Ask what is still open, when a defects period ends or what retention is outstanding, and it answers from the record. It will not tell you whether something is your liability, or how long you are on the hook — those depend on a contract and on facts it cannot see.

Try it on a real job

The free plan runs one project end to end — the fastest way to find out whether any of this fits how you work.